1.
Which of the following schedule compression techniques is often
the lowest risk and with the added benefit of lowering the cost?
2.
The major disadvantage of using a bar chart on large projects is
that bar charts:
3.
Which of the following network diagramming methods do not use
dummy activities?
4.
Which of the following activity-on-arrow network diagramming
methods does not require three estimates for durations?
5.
Which of the following is false concerning the critical path in
a network?
6.
Which of the following scheduling techniques is most appropriate
today for managing a project?
7.
Which type of chart provides the least “predictive” value?
8.
Which of the following is normally not one of the three critical
parameters provided in information reporting to the customer?
9.
Which of the following scheduling techniques is most appropriate
today for managing a project?
10.
A charting technique designed to illustrate the inductive and
deductive reasoning necessary to achieve some objective is called a _____ Diagram
/ network
11.
An employee earning $40/hour works in a department where the
overhead is 125%. A billable or charge back hour to this department would be:
12.
When a functional manager tells you that your project is 10%
more difficult than the standard project, the functional manager is providing
you with a _____ estimate.
13.
Which of the following is generally not part of capital
budgeting?
14.
Material provided in a proposal to justify one’s estimates are
called:
15.
Which of the following components of life cycle costing incurs
the largest cost?
16.
Which of the following projects would most likely have
reasonably good estimating techniques?
17.
Which of the following standard project estimating techniques is
usually accomplished in weeks?
18.
Pricing out the construction cost of a home by a cost per square
foot would be representative of a _____ estimate.
19.
The person or group with greatest ability to influence cost at
project initiation is:
20.
An S-Curve plots:
21.
Which of the following terms is used to determine the trend on
cost?
22.
The weakness in all of earned value measurement is the way we
calculate:
23.
In which type of project report would we most likely find EAC
and ETC?
24.
Variance envelopes are usually established because:
25.
If PV = $100, EV = $200 and AC = $300, the status is:
For The Students Who Need Grade ‘A’ In Their Studies
Hi, hope you are having a great day…
We are a group of 24 writers having
profound expertise in Business and Computer Science subjects. We can help you
score A grade in your Accounting, Marketing, Finance, Economics, Management,
Mathematics, Statistics, Information System, System Modeling, C++, Java
Programming, Network Administration, Enterprise Administration, Database, Web
Design, Networking, Internetworking, Data warehouse etc…
We can also provide help with Psychology,
Nursing, Health, History, English Literature, Political Science, Ethics,
Humanity etc classes.
We can help with essays, term papers,
research papers, dissertation, Ilabs, mymatlab, Wileplus, quizzes, exams,
discussion questions etc.
You can expect:
We understand each student has different
requirement and we tend to treat each student according to his/her
satisfaction.
We will provide original assignments,
plagiarism free and to custom requirement.
We will always meet deadlines.
Our support will be 24/27, even in
holidays.
Our pricing will be fair.
We will do free revisions if you want to
make changes in provided work.
Email us for more information, query and
quote.
No comments:
Post a Comment